200 N. Dearborn

Phase 1 for 200 Dearborn: Two (2) 250 Ton Chillers that was disassembled in the shop after delivery. We then delivered to the site on Friday, May 4, 2018, and brought up the sections on a standard freight elevator eliminating the need for cranes, helicopters and street closures. The first chiller is scheduled to go online by Tuesday, May 15, 2018, and the second chiller by Wednesday, May 30, 2018, so the customer can get the full Com Ed rebate.

Project Information

Project Name: Private Residences – Chiller Replacement

Location: 200 N. Dearborn St., Chicago, IL

Completion Date: June 2018

Architect: N/A

Engineer: AMS Mechanical Systems, Inc.
Thomas E. Kelleher, PE, LEED AP

Contractor: AMS Mechanical Systems, Inc.

Project Manager: Randall Byerley

Project Type: Chiller Replacement

Trades: Mechanical Piping & Electrical